Completion of restoration works for a cycle/pedestrian bridge over the Idice river in San Lazzaro (BO)

 

17 luglio 2025

After about one year of intense activity, made more complicated by two flood events, the refurbishment and strengthening works for the cycle/pedestrian bridge over the Idice river along via Pedagna in San Lazzaro (BO) have been completed.

The inauguration was held at the presence of the major of San Lazzaro, the Mobility councillor, the representatives of the contractor, AhRCOS S.p.A., and some of ENSER professionals, who were responsible for the design, construction management and safety coordination activities.

The works, started in July 2024 and financed by both municipality resources and PNRR funds, for a total cost of €430'000, were concluded one month ahead of schedule.